Quick answer
Protection coordination compliance means proving to the network operator that your protection clears faults selectively and that your generator disconnects when the grid rules say it must. The evidence is a fault study, a coordination study, a settings schedule and interface protection settings to G99 in Great Britain or IEEE 1547 in the US, then witnessed commissioning tests.
Key takeaways
- In Great Britain, loss of mains protection must use rate of change of frequency set at 1 Hz per second with a 0.5 second delay; vector shift is no longer accepted.
- The settings schedule is what the network operator checks against the relays on site, so every number in it has to match the study and the commissioning test sheets.
- Most delays come from missing data, such as transformer impedances or the operator's source fault level, not from the modelling itself.
The network operator has written back: before it energises your solar farm, battery or generator, it wants evidence that the protection is right. That evidence is protection coordination compliance. It shows that faults inside your site are cleared by your own devices without tripping the network, and that the plant disconnects when the grid rules say it must. In Great Britain the rules are G99; in the US they are IEEE 1547 and the utility's own requirements.
Until that evidence is accepted, the site does not get energised. That is why this is the part of a connection project most likely to hold up the date. This page is for developers, asset owners and project managers with a connection offer in hand, and it covers what the operator checks, what goes in the submission and why packs get sent back. If you want the basics first (what coordination is, and how relay grading works), start with what protection coordination is.
If you already have a request from the network operator, send us the single line diagram and the relay settings and an engineer will tell you what the submission needs. Our UK power system studies team prepares these for generation and storage connections.
What the network operator is checking
The operator is checking two separate things.
The first is that your protection coordinates. A fault inside your site must be cleared by your own devices, quickly and selectively, without tripping the operator's breaker upstream and taking other customers off supply with you. Fault and coordination studies prove it.
The second is that your connection meets the rules for that network. For a generator, that means interface protection: relays at the point of connection that disconnect the plant if voltage or frequency go outside set limits, or if the grid itself disconnects and the plant risks running on alone (islanding). These settings are written into G99 or the utility's requirements, and the operator expects to see them exactly.
A scheme can pass the first check and fail the second. Well-coordinated protection with an out-of-date loss of mains setting is still non-compliant.
The evidence pack, study by study
| Study or document | What it proves | What the operator receives |
|---|---|---|
| Short circuit (fault level) study | How much fault current flows at each point, and that breakers and switchgear can interrupt it | Fault levels at each busbar; equipment rating check |
| Protection coordination study | Devices grade correctly, so only the nearest one trips | Time current curves and the grading margin for each pair of devices |
| Protection settings schedule | The settings that will be programmed into each relay | A schedule the operator checks against the relays on site |
| Interface protection design | The plant disconnects for abnormal voltage, frequency or loss of mains, within the required limits | Settings set against G99 tables (GB) or IEEE 1547 and utility requirements (US) |
| Arc flash study, where asked | The heat a worker would face at each panel, and the clothing needed | Incident energy and boundaries; labels |
| Commissioning test records | The relays on site trip at the settings in the schedule | Secondary injection test sheets, often witnessed |
The order matters. The fault study feeds the coordination study, the coordination study produces the settings schedule, and the commissioning tests prove the schedule. Run them out of order, or by different people with different models, and the numbers stop agreeing. Arc flash and coordination pull against each other, because a longer delay keeps the scheme selective but lets more energy into an arc, so the two should be set from the same model (see arc flash studies for solar, wind and battery storage sites).
If your operator has asked for any of these and you are not sure what you already hold, send the request and your single line diagram to sales@severnde.co.uk (UK) or sales@renewable-d.com (US). An engineer will tell you which parts are missing.
What G99 asks for in Great Britain
Engineering Recommendation G99 covers generation and storage connecting to distribution networks in Great Britain. The protection it asks for sits at the connection point and trips the plant for:
- under and over voltage
- under and over frequency
- loss of mains, meaning the grid supply has gone and the plant is feeding a section of network on its own
The settings come from tables in G99, and the network operator checks your schedule against them line by line.
Loss of mains is where older schemes trip up. After the Accelerated Loss of Mains Change Programme, vector shift protection is no longer accepted for loss of mains in Great Britain, and sites that used it were required to replace it. Where rate of change of frequency (RoCoF) protection is used, the setting is 1 Hz per second with a 0.5 second delay. A settings schedule copied from an older project can still carry the old method, and the operator will send it back.
For larger sites the network operator usually witnesses the commissioning tests, so the relays are injected with test signals in front of them and shown to trip at the scheduled values. Very large power stations also have to meet the Grid Code, which the national electricity system operator runs.
What US utilities ask for
In the US, distributed energy resources connect under IEEE 1547-2018, which sets voltage and frequency trip and ride-through requirements and anti-islanding. Each utility adds its own interconnection requirements on top, including the settings it wants and how it witnesses tests. Larger plants connected to the bulk power system also fall under NERC reliability standards. The coordination study itself usually follows IEEE 242, the Buff Book, and the fault study IEEE or IEC 60909 methods.
Why submissions get sent back
Packs usually come back because the documents disagree with each other. The time multiplier in the settings schedule does not match the curve in the study, or the single line diagram predates the last change on site, or the interface settings were lifted from an older version of the rules. Each one is small. Each one costs a round of comments.
Missing data is the other cause. A study needs transformer impedances, cable lengths and sizes, the fault contribution of each inverter or generator, and the operator's own source fault level at the connection point, and when any of those are guessed the operator will usually ask where the number came from. Each round of questions adds time. Collecting the data before the modelling starts is the cheapest time saving on the whole project.
How long does compliance take?
Longer than the modelling. The studies themselves are a modest part of the time; waiting for data, operator comments and a witness test date makes up most of the rest. Book the commissioning witness test early, because the operator's diary is often the last thing to fall into place.
What we need from you
- The connection offer and any protection requirements the network operator or utility has sent.
- The single line diagram, as built or as designed.
- Equipment data: transformer ratings and impedances, cable schedules, inverter or generator fault contribution, CT ratios.
- Existing relay settings, if the site is already running.
- The operator's fault level data for the connection point, if you have it.
What to do next
- Read the operator's request and list each document it asks for.
- Check that your single line diagram matches the site as it is now.
- Send both to an engineer before the modelling starts, and ask which data is missing.
Has your network operator asked for protection studies before it will connect you? Our UK consultancy team prepares the fault, coordination and interface protection studies and the settings schedule from one model, so the documents agree with each other. Send the operator's request and your single line diagram, and an engineer will tell you what the submission needs. Send an enquiry, email sales@severnde.co.uk (UK) or sales@renewable-d.com (US), or call +44 116 279 6131 (UK) or +1 414 562 6559 (US).
Frequently asked questions
What does a network operator need to approve the protection on a grid connection?
Usually a current single line diagram, a short circuit study, a protection coordination study with time current curves and grading margins, a protection settings schedule that matches it, and evidence that the interface protection meets G99 in Great Britain or IEEE 1547 and the utility's rules in the US. Commissioning test records, often witnessed by the operator, complete the evidence.
What standards govern protection coordination compliance?
In Great Britain, Engineering Recommendation G99 governs generation connecting to distribution networks, with loss of mains, voltage and frequency protection settings, and larger plants must also meet the Grid Code. In the US, IEEE 1547-2018 sets interconnection requirements for distributed resources, alongside the utility's own rules and, for larger plants, NERC reliability standards. IEEE 242 is the usual guide to coordination practice.
Is vector shift protection still allowed under G99?
No. Following the Accelerated Loss of Mains Change Programme in Great Britain, vector shift is no longer accepted as loss of mains protection, and existing sites using it were required to remove or replace it. Where rate of change of frequency protection is used, the setting is 1 Hz per second with a definite time delay of 0.5 seconds.
Tags
Working on a project like this?
Talk to our engineering team about your site, your grid connection or your power quality problem.
Get in touch


