Co-locating battery storage at an existing wind or solar farm
    Grid Technology

    Co-locating battery storage at an existing wind or solar farm

    Renewable Energy & Drives
    November 19, 2026

    A battery at a wind or solar farm you already own can reuse its connection, substation and reactive power kit. What the network asks and what changes.

    Quick answer

    Co-located battery storage means adding a battery behind the grid connection of a wind or solar farm that is already running. It can reuse the connection agreement, the substation and often the reactive power equipment. It still needs the network operator's agreement. Under connections reform the change is a gated modification, so the application waits for an application window, and the battery is tested for compliance as a unit of its own.

    Key takeaways

    • Adding a battery counts as adding a technology under connections reform, so the application can only go in while a gated application window is open, and the battery may be given a later connection date than the farm.
    • NESO treats the battery as a separate unit that must meet the current Grid Code, even where the turbines or panels beside it were connected under older rules.
    • A battery needs import capacity to charge from the grid, which a connection agreement written for generation may not include.

    Your wind farm fills its export capacity only on windy days, or your solar farm sends nothing at night, and someone has asked whether a battery could use the spare room. In most cases it can, without a new grid connection. The battery goes behind the connection you already have. The network operator still has to agree to the change, though, and since connections reform the application can usually only go in when an application window is open. The battery is also tested as a unit in its own right.

    This page is for owners and asset managers of operating wind and solar farms in Great Britain who are weighing up a battery. It covers why co-location appeals, what the network operator will ask for and when, which parts of the site can be reused and what has to be checked, and the reactive power question in particular. If you are at the early stage, send us the connection agreement and the single line diagram and an engineer will tell you what the battery would mean for the site. Our power system studies team runs the studies co-location needs, and our battery storage page covers the storage side.

    Why co-location appeals

    The grid connection is the scarce part of any energy project, and you already have one. A battery can charge when the site or the grid has power to spare and export into the capacity the farm leaves unused.

    The site also brings the expensive civil and electrical work with it: the substation, the transformer, the switchgear, the cable route to the network, the land and the access. A new battery project has to buy or build all of that, and join the connection queue for the privilege.

    What the network operator will ask for

    The route depends on where the farm connects.

    For sites connected to the transmission network, NESO's guidance on co-location applies. Putting a battery behind your existing connection point is what NESO calls a consolidated connection, and it needs a modification application to review the existing connection agreement before the battery connects. The battery is treated as a separate unit with its own technical requirements. Compliance can be shown at the connection point using both technologies together, but the site must also comply with the battery running alone and with the generation running alone. Detailed computer models of the battery are required as part of that.

    There is one point that surprises owners. The battery is tested against the current Grid Code, even if the turbines or panels beside it were connected under older rules. Equipment chosen to an older site's specification is not always good enough.

    For smaller sites connected to a distribution network, the conversation is with the local network operator instead. Expect an application to change the connection and a G99 assessment for the battery, the same compliance process any new generator goes through. If the farm is large enough that the change has to be assessed for its effect on the transmission network, the network operator also applies to NESO on your behalf.

    Then there is timing. Connections reform, introduced in 2025, changed when you can apply. Adding a battery counts as adding a technology type, even when it sits behind the meter and stays inside the export capacity you already have. NESO classes that as a gated modification, whether you apply to NESO directly or your network operator applies for you. The application can only be submitted while a gated application window is open, and one sent at any other time is rejected. The battery also has to meet the Gate 2 readiness criteria, such as land rights and planning, in its own right.

    NESO then decides whether the change is material: whether it changes how much the site imports and exports and when, adds fault current, or adds safety or constraint risk. If it does not, the battery can go ahead on the existing terms. If it does, the battery is studied with the other applications from the same window and given a later queue position. Where the battery's effect can be separated from the farm's, only the battery is restudied and the farm's own terms stay as they are. NESO expects most technology changes to count as material, so plan on the battery connecting later than the engineering alone would allow. Ask NESO or your network operator when the next window opens before you build the battery into a programme.

    Whichever route applies, two capacity questions come first. Can the battery's export fit inside the agreed export capacity alongside the farm's own output, and does the agreement allow the site to import from the grid to charge? A connection agreement written for a generator sometimes allows only a small import for auxiliary loads.

    What can be reused, and what has to be checked

    Almost everything in the substation can stay. Almost everything has to be checked.

    Part of the siteUsually reused?What has to be checked
    Connection agreementYes, amendedExport capacity, import capacity for charging, any export limiting scheme
    TransformerOftenRating with power flowing both ways, and a heavier daily load cycle
    SwitchgearOften, with a new bayA spare bay for the battery, and fault ratings with the battery's extra fault current
    ProtectionSettings changePower now flows both ways and the battery adds fault current
    Reactive power equipmentOftenCoordination with the battery inverters, and the reactive studies rerun
    Metering and controlsPartlySeparate metering for the battery, site controller, any subsidy metering rules

    The protection changes catch projects late. Our explainer on what protection coordination involves shows why a new source of fault current means new settings.

    Whether the battery couples on the AC side or shares the solar inverters on the DC side changes several rows of that table. Our article on solar and battery integration compares the two.

    The reactive power question

    Many wind and solar farms have reactive power equipment, a STATCOM or an SVC, to hold the voltage at the connection point within the limits in the connection agreement. Adding a battery raises two questions about it.

    The first is whether it is still needed. A STATCOM supplies reactive power and cannot push real power. A battery inverter can do both, within its rating. Some newer generation equipment can also meet the reactive requirement by itself. So the battery can take over some of the reactive duty, but the site still has to meet the requirement with the battery out of service, because NESO expects compliance with each technology alone. On many sites that means the STATCOM stays.

    The second is coordination. Two devices both trying to control the voltage at the same point can fight each other, each reacting to the other's correction. The control settings of the STATCOM and the battery inverters have to be set to work together, and the reactive power studies rerun for every combination of plant in and out of service.

    Adding a battery is a good moment to look at the condition of the STATCOM. If it is ten or fifteen years old, find out now whether its controls and spares will last as long as the battery. Often a repair or a control upgrade keeps it going for much less than a new unit costs. See our pages on STATCOM repair and service and STATCOM control upgrades.

    If you want a view on what your substation can take before you talk to a battery supplier, send the connection agreement, the single line diagram and the transformer and reactive equipment details to sales@severnde.co.uk (UK) or sales@renewable-d.com (US), and an engineer will tell you which studies the network operator is likely to want.

    The studies that change

    Adding a battery reopens most of the studies done when the farm was connected: load flow, fault level, protection coordination, reactive power capability, harmonics under G5/5 for the new inverters, and the dynamic simulations the Grid Code or G99 requires. None of them starts from scratch. The existing site model is the starting point, which saves time against a new site.

    The commercial side, briefly

    Who owns the battery changes the paperwork. It can sit in the same company as the farm, or in a separate company that shares the connection under an agreement. Sites earning Renewables Obligation or Feed-in Tariff income have to follow Ofgem's rules for storage on accredited sites. Leases, planning and lenders' consents all need checking. Take legal advice early, alongside the engineering.

    What to send us

    • The connection agreement and any later variations
    • The single line diagram and substation layout
    • Transformer nameplate and recent test results
    • The reactive power equipment: type, rating, age and any service history
    • A year of half-hourly export data, if you have it
    • The battery size you have in mind, if you have one

    What to do next

    1. Read the capacity terms in your connection agreement. Export, import and any limiting scheme decide how big the battery can be.
    2. Check the substation before you size the battery. The transformer, a spare bay and the protection set the practical limit.
    3. Look at the reactive equipment now. Its condition and its controls affect the compliance case for the whole site.

    Thinking about adding a battery to a wind or solar farm you already run? Our UK studies team works through the connection agreement, the substation and the reactive power equipment and tells you what can be reused and what the network operator will want. Send us the connection agreement and the single line diagram, and an engineer will tell you which studies the battery would need. Send an enquiry, email sales@severnde.co.uk (UK) or sales@renewable-d.com (US), or call +44 116 279 6131 (UK) or +1 414 562 6559 (US). Our renewables page covers the rest of what we do for operating sites.

    Frequently asked questions

    Can I add battery storage to an existing solar farm without a new grid connection?

    Often, yes. The battery can sit behind the existing connection point and share its capacity, but the network operator still has to agree. Adding a battery is a gated modification under connections reform, so for a transmission-connected site the application to NESO can only be made during a gated application window. For a distribution-connected site the network operator will want an application and a G99 assessment, and larger sites go through the same windows.

    Does a co-located battery need its own grid code compliance?

    Yes. NESO's guidance treats the battery as a separate power park module and expects it to comply with the current Grid Code, even where the existing generation was connected under older rules. The site has to comply with the battery alone, the generation alone and both together, though a reduced set of combined tests may be agreed.

    Can a battery share the STATCOM at a wind farm?

    Often it can. The STATCOM keeps supplying reactive power to hold the voltage, and the battery inverters add real power and some reactive capability of their own. The controls of the two have to be coordinated so they do not fight over the voltage, and the reactive power studies have to be rerun for each combination of plant in and out of service.

    Tags

    co-locate battery storage wind farmco-located battery storageadd battery storage to existing solar farmco-location bess wind farmconnection sharing storagebattery at existing renewable site

    Working on a project like this?

    Talk to our engineering team about your site, your grid connection or your power quality problem.

    Get in touch
    GET IN TOUCH

    Let's Solve Your Power Challenge.

    Send an enquiry to our engineering team. We'll help you identify risks and uncover efficiency opportunities.

    North America

    Renewable Energy & Drives

    5325 S Moorland RdNew Berlin, WI 53151United States

    UK & Europe

    Severn Drives & Energy

    Units 2 & 3, Kingsley Business ParkNew Road, Kibworth BeauchampLeicestershire, LE8 0LEUnited Kingdom

    Send an enquiry

    Fill out the form below and we'll be in touch.