Leading Grid Connection Engineering Options for UK Energy Projects
    Grid Technology

    Leading Grid Connection Engineering Options for UK Energy Projects

    Raveenthan Thambirajah
    July 9, 2026

    What a UK energy project needs from grid connection engineering: the G99 application, DNO and NESO steps, the studies, and how to choose a partner.

    Quick answer

    A UK energy project needs grid connection engineering at three points: before it applies, to secure and keep its connection offer, and before the network switches it on. Generation and storage on the distribution network go through the local distribution network operator (DNO) under Engineering Recommendation G99. Transmission-connected sites go through NESO, the national system operator, under the Grid Code. Under the 2025 queue reform, Gate 2 readiness also decides who gets a firm date.

    Key takeaways

    • G99 bands sites by size: Type A up to 1 MW, B from 1 to 10 MW, C from 10 to 50 MW, and D at 50 MW and above or at 110 kV and higher. Each band adds compliance work.
    • Ofgem extended the deadline for the first Gate 2 transmission offers twice in 2026, most recently to 31 October. Distribution offers in that first phase are due by 30 November 2026, and a second phase of offers runs into early 2027.
    • Sites that only import still need power quality and protection studies when they add large motors, drives or chargers, even with no G99 generation application.

    You have a solar, wind or battery site to connect in Great Britain, or a large new load, and a network operator who will judge it on study reports. Most of the work sits with the DNO, the company that runs the local network, and is set by G99, the engineering rulebook for connecting generation and storage. Sites connected to the transmission network deal with NESO, the national system operator, and the Grid Code instead. If you already hold an offer, send it to our UK studies team and we will tell you which studies it triggers.

    This page is for developers and industrial sites in Great Britain planning solar, wind, battery storage or a large new load. It covers the options for getting the engineering done, how G99 and the network operators shape it, the steps from application to energisation, and where Gate 2 has left the queue as of November 2026.

    What are the leading grid connection engineering options for UK energy projects?

    You have three options: your own engineers, an application or planning consultant, or a specialist power system study firm. For most generation and storage projects, the study firm is the one that carries the risk, because the network operator judges the project on the study reports.

    Whoever does it, the package needs these parts:

    WorkstreamUK contextWhy it matters
    Connection feasibility and impact studyDNO enquiry or the transmission processConfirms capacity, voltage level and reinforcement early
    G99 or Grid Code complianceDistribution or transmissionSets the ride-through, protection and control obligations
    Protection coordinationSite and network relaysPrevents nuisance trips and uncleared faults at the connection point
    Reactive power and voltage controlThe power factor limits in the offerShows the plant can hold its voltage obligations
    Power quality and harmonicsG5/5, P28 and P29 limitsAvoids late filters and holds on energisation
    Industrial load studies, where relevantMotor starting, flicker, drivesClears import-only sites that still stress the network

    Buying these as separate reports from different firms looks flexible. It usually creates rework, because every study depends on the same network model and the same assumptions about the offer. G5/5, P28 and P29 are the ENA documents that set the limits for harmonics, flicker and phase unbalance.

    How do G99, DNOs and NESO shape the engineering?

    The route depends on the voltage you connect at and whether the site exports.

    Distribution-connected generation and storage connect through the local DNO under G99. Very small units, up to 16 A per phase (about 3.68 kW on a single phase), fall under G98 instead. Above that, G99 bands the site by size. Type A runs up to 1 MW. Type B is 1 to 10 MW, Type C is 10 to 50 MW, and Type D is 50 MW and above, or any site connected at 110 kV or higher. Each step up adds protection and control requirements and more test evidence. The larger types also get a staged sign-off instead of a single commissioning visit.

    Transmission-connected sites follow the Grid Code through NESO, the National Energy System Operator. The engineering logic is the same, though the studies are larger and take longer, and reinforcement is more often part of the offer.

    Industrial sites that only import may need no G99 application at all. They still need power quality and protection studies, and sometimes reinforcement, when large motors, drives or chargers change the load. Demand connections of 5 MVA and above have needed a fuller application since 1 June 2026, with a site plan, a project timeline and, where large motors, drives or chargers are involved, a single line diagram. Our article on grid connection for electrification projects covers that route.

    If you need G99 grid connection support and your offer lists studies you are not sure about, send it with the single line diagram (the drawing of how the site's equipment connects) to sales@severnde.co.uk and an engineer will tell you what each study needs from you.

    From application to energisation: the UK steps

    The path is broadly the same for a battery, a solar farm or a wind site:

    1. Feasibility. Check spare capacity, fault level and the likely connection point before land and equipment are committed.
    2. Application. Apply to the DNO for a distribution connection, or to the system operator for a transmission one. The application fixes your import and export figures.
    3. Connection offer. The offer sets the connection point, the capacity, the cost of any reinforcement, and the studies and deadlines that come with it.
    4. Gate 2 evidence. To hold a firm date under the reformed queue, you show readiness, meaning secured land rights, by the deadlines in the offer.
    5. Detailed design and compliance studies. Protection, reactive power, harmonics and the G99 or Grid Code evidence, built on the actual equipment.
    6. Commissioning and compliance tests. The network operator witnesses tests and checks the results against the studies.
    7. Energisation and permission to operate. Small sites get one sign-off. Larger ones move from interim to final permission as each set of test results is accepted.

    Timescales are set mostly by steps 3 and 4, and then by equipment. A large power transformer is quoted at more than two years at the moment, which often matters more than the study time. Our article on why grid connection projects get delayed goes through where the months go, and the battery-specific studies are on our page about BESS grid connection services and studies.

    Gate 2 and the connections reform, as of November 2026

    Ofgem approved the reform in April 2025. It replaced first come, first served with a test at "Gate 2": projects that show secured land rights and fit the government's Clean Power 2030 plan get a firm date and connection point, and the rest wait at Gate 1.

    The new offers have taken longer than planned. NESO's timetable put the first transmission offers between May and September 2026. Ofgem, the energy regulator, then extended that deadline twice in 2026, most recently to 31 October, for the last 62 or so offers. Distribution offers in that first phase are due by 30 November 2026, and a second phase of offers runs into early 2027. If your project is still waiting, our article on the grid connection queue and private wire covers one alternative for sites with a large user nearby.

    What does a strong UK connection engineering package include?

    A package that gets you to energisation usually has six parts:

    1. Early feasibility, with a realistic MW and MVA figure before land and equipment are fixed.
    2. An impact study matched to the application, set out the way the network operator expects.
    3. Compliance design for G99 or the Grid Code: control modes, fault ride-through, loss of mains protection and reactive capability.
    4. Protection coordination that works with both the network and any existing site protection.
    5. Harmonic and flicker analysis, especially for inverters, drives or large motors.
    6. One evidence pack, so the commissioning tests trace back to what was studied.

    For battery storage, add import and export cases, because a battery is demand when it charges. For industrial loads, add motor-starting and drive harmonic cases even when export is zero.

    How should UK developers choose a provider?

    Choose a firm that can run the network studies and design the site's electrical system together. Application and planning support have their place, but they do not set protection relays, specify a harmonic filter or produce a compliance pack that survives the witness test.

    Ask four questions. Has the firm taken G99 or Grid Code compliance packs through to energisation? Can it model industrial loads and inverter behaviour as well as steady export? Will the connection, protection and power quality studies share one network model? And if your portfolio spans the UK and the US, can it work to both sets of standards? Our guide to choosing outsourced grid connection engineering support lists the documents to ask for.

    Renewable Energy & Drives runs its UK studies through its sister company, Severn Drives & Energy, whose team works from Kibworth, Leicestershire.

    What to send us

    On existing sites the drawings are often out of date, or miss changes made since they were drawn, so tell us what you know is uncertain. Send what you have of:

    • the connection offer, or the network operator's letter
    • the single line diagram
    • what is being connected (generation, storage or load) and its size in MW and MVA
    • the site location and the connection voltage
    • the inverter, drive or motor datasheets, if chosen

    What to do next

    1. Find your route. Distribution or transmission, and which G99 type, decide the scope.
    2. Check your Gate 2 deadlines. Missing a readiness date can cost you the firm date.
    3. Commission the studies before ordering equipment. The results can change what you buy.

    Holding a UK connection offer, or about to apply? Our UK studies team at Severn Drives & Energy, the UK sister company of Renewable Energy & Drives, runs G99, harmonic, fault level and protection studies from Kibworth, Leicestershire, for sites across the UK. Send us the connection offer or the network operator's letter with the single line diagram, and we will tell you which studies it triggers and what we need to start. Send an enquiry, email sales@severnde.co.uk (UK) or sales@renewable-d.com (US), or call +44 116 279 6131 (UK) or +1 414 562 6559 (US). More about the UK team is on the Severn Drives & Energy page.

    Frequently asked questions

    What are the leading grid connection engineering options for UK energy projects?

    There are three: your own engineers, an application or planning consultant, or a specialist power system study firm. The strongest option for most projects is one firm running the connection study, G99 or Grid Code compliance, protection, reactive power and harmonic studies on one network model, because every report depends on the same assumptions and the network operator reads them together.

    Is G99 always the standard that applies in Great Britain?

    G99 applies to generation and storage connecting to distribution networks above the G98 limit of 16 A per phase. Smaller units fall under G98. Plant connected to the transmission system follows the Grid Code through NESO, the system operator. Confirm the voltage level and whether the connection is distribution or transmission before scoping the compliance work.

    How long does a UK grid connection take for a battery storage or solar project?

    It depends on the queue more than the engineering. Firm dates are being reissued through the Gate 2 reform: the first transmission offers were due by 31 October 2026, first-phase distribution offers by 30 November 2026, and a second phase runs into early 2027. Studies, design and G99 compliance must finish before that date, and transformer lead times above two years often set the pace.

    Tags

    Grid ConnectionUK EnergyG99DNOGrid Integration

    Working on a project like this?

    Talk to our engineering team about your site, your grid connection or your power quality problem.

    Get in touch
    GET IN TOUCH

    Let's Solve Your Power Challenge.

    Send an enquiry to our engineering team. We'll help you identify risks and uncover efficiency opportunities.

    North America

    Renewable Energy & Drives

    5325 S Moorland RdNew Berlin, WI 53151United States

    UK & Europe

    Severn Drives & Energy

    Units 2 & 3, Kingsley Business ParkNew Road, Kibworth BeauchampLeicestershire, LE8 0LEUnited Kingdom

    Send an enquiry

    Fill out the form below and we'll be in touch.