What Ofgem's data centre readiness tests mean for electrical design
    Grid Technology

    What Ofgem's data centre readiness tests mean for electrical design

    Renewable Energy & Drives
    November 19, 2026

    Ofgem has proposed a fee per MW and new milestones for data centres in the GB connection queue. What they would force you to fix in the electrical design.

    Quick answer

    Ofgem has proposed two tests for data centres in the Great Britain connection queue: a returnable fee of £237,500 to £712,500 per MW for projects of 40 MW and above, and milestones asking for evidence of a customer, of long-lead equipment orders and of a certified design. On 19 November 2026 both were still proposals.

    Key takeaways

    • The fee is secured per MW requested and is forfeited if the project reduces capacity before energisation, so the load estimate becomes a financial commitment.
    • At the second data centre milestone you would have to show a binding order for equipment such as transformers or switchgear, with its voltage, rating and delivery date.
    • By the sixth, the design would need certifying against EN 50600, TIA-942 or an Uptime Institute Tier certification of design documents.

    You are developing a data centre in Great Britain and you hold, or are about to apply for, a demand connection. Under proposals Ofgem published in July 2026, keeping that place in the queue would cost money and come with evidence deadlines: a customer, firm orders for transformers or switchgear, and an independently certified design. On 19 November 2026 they were still proposals, but the design work behind them takes months.

    This page is for data centre developers, investors and their engineering teams with a demand connection in the queue, or about to apply. It explains what Ofgem has proposed, what each test would make you fix in the electrical design, and when. If you have an offer or an application in hand, send us the connection details and your single-line diagram and an engineer will tell you which studies and long-lead items the milestones are likely to need.

    Why Ofgem is doing this

    The demand queue has grown faster than anyone can build for. Contracted demand rose from 41 GW in November 2024 to 125 GW in June 2025. Ofgem's analysis puts about 73 GW of the queue down to data centres, across around 315 projects ranging from 1 MW to 1,500 MW. Peak demand for the whole of Great Britain in 2025 was 45 GW.

    Ofgem's view is simple. It is cheap to hold a place in that queue, so speculative projects sit in it and block viable ones. The two proposals are meant to make holding a place cost something and to check that projects are really progressing. Ofgem consulted on them from 29 July to mid-September 2026 and said it intends to decide later in 2026.

    The commitment fee turns the MW request into money

    Data centres of 40 MW and above that connect to the transmission network, or to a distribution network under a transmission assessment, would have to secure a fee of between 2.5% and 7.5% of average project cost. Ofgem puts that average at £9.5 million per MW, which gives about £237,500 to £712,500 per MW requested. A 100 MW project would secure between £23.8 million and £71.3 million.

    The fee is held from the day you accept a connection offer until energisation. It comes back if the project proceeds as planned.

    It is lost if the project terminates, reduces its capacity before energisation, or fails the other requirements.

    That changes how the capacity request should be worked out. Today it is tempting to ask for generous headroom. Under the fee, every padded megawatt would be money at risk, and cutting capacity later would forfeit it. The request needs to come from a real load model: IT load by phase, cooling at the hottest design day, losses in transformers and UPS, and the ramp from first hall to full build.

    The new milestones, and what each one forces in the design

    Ofgem proposes three data-centre-specific milestones on top of the existing queue milestones. For the milestones, its favoured threshold is 10 MW of rated IT load, so they would reach far smaller projects than the fee.

    MilestoneWhenWhat you would need to showWhat it fixes in the electrical design
    M0.5Before the first existing milestone, soon after accepting the offerYour business model (self-operated, or lease or sale) and non-binding evidence of a compute customerThe demand you are designing for, and its phasing
    M2At the existing second milestoneA genuine, material commitment to buy the electrical equipment needed to connect and operate, such as transformers or switchgearConnection voltage, transformer configuration, switchgear ratings: in effect a frozen single-line diagram
    M6At the existing sixth milestone, when the construction plan is agreedFinancial capability, a design certified against a recognised data centre standard, and for lease or sale projects a binding customer contractThe full power distribution design, redundancy and backup

    The existing queue milestones already run to a timetable. As one example from Ofgem, a project due to connect in two to three years has to meet the first one at least 18 months before its connection date. Miss a milestone and the project can lose its place.

    The long-lead equipment test needs a fixed design early

    The M2 test is about orders. Intentions do not count.

    Ofgem lists the evidence it expects: the equipment, the intended connection voltage, the rating, the supplier, the date of the commitment, the expected delivery date and, where relevant, the value. A purchase invoice, an executed contract or a binding supplier commitment would count. The system operator or the network operator would then judge whether what you have bought makes sense for the connection you hold.

    So by M2 the decisions behind the order have to be made. All of them. Which voltage you take the supply at. Whether you use one large transformer or several smaller ones. What fault level the switchgear must withstand, and how the site is split for maintenance and redundancy. Those come from studies of the connection, and they are hard to change once steel is ordered.

    The timing is tight. The equipment is slow. Large power transformers average around two and a half years from order, and medium voltage switchgear runs from under a year to much longer on custom orders, as our page on transformer and switchgear lead times sets out. If the site already has transformers or switchgear, test them before you plan around new ones, and ask the network operator how reused equipment would be treated as evidence.

    If you are approaching M2 and the single-line diagram is not frozen, email it with the connection offer to sales@severnde.co.uk and an engineer will tell you which studies still stand between you and a safe order.

    The certification test needs the backup design done by M6

    At M6 the design itself would be tested. Ofgem proposes that one of three independent assessments would satisfy it: EN 50600 (whose part 2-2 covers power supply and distribution), TIA-942 design certification, or an Uptime Institute Tier certification of the design documents. Each looks at the electrical design in detail, including how the site keeps running through failures and maintenance.

    In practice that means the UPS, the backup generation, the switchboards and the distribution have to be designed by the time the construction plan is agreed. A budget line will not pass. On data centre builds the UPS is often specified last, and in our own enquiries this year large data centre UPS requests have arrived late and urgent. Under these milestones that habit would hold up certification, and with it the project. Our comparison of medium voltage and low voltage UPS is a starting point for the whole-facility choice.

    If the queue still does not fit your programme

    Some projects will find the fee, the milestones or the connection date unworkable. On-site generation, storage and a private wire from a generator nearby can bring a first phase online and let the grid connection follow in steps. Our GridLink private wire lets a site keep its grid connection and take private wire power alongside it. Our article on grid connection queue delays and private wires compares the routes.

    Note that Ofgem did not take forward flexibility as a readiness test, so offering to be flexible will not count as evidence of readiness on its own.

    Four things to do now

    1. Build the load model that your MW request will rest on, phase by phase, before you accept an offer.
    2. Freeze the connection design early: voltage, transformer arrangement and switchgear ratings, backed by studies, so the M2 order is the right one.
    3. Choose your certification route and design the power system to it from the start, including the UPS.
    4. Check the timetable against your offer's milestones, and track the Gate 2 dates in our article on what to do with a Gate 2 offer.

    Developing a data centre in Great Britain and want the electrical side ready for the milestones? Our UK team at Severn Drives & Energy in Kibworth, Leicestershire, runs the power system studies behind a connection design, and we supply UPS systems up to whole-facility medium voltage scale. Send us the connection offer or application, your load estimate and the single-line diagram, and an engineer will tell you which studies and long-lead items the milestones are likely to need and where the backup design has gaps. Send an enquiry, email sales@severnde.co.uk (UK) or sales@renewable-d.com (US), or call +44 116 279 6131 (UK) or +1 414 562 6559 (US). More on our work for the sector is on the data centres page and the Severn Drives & Energy page.

    Frequently asked questions

    How many data centres are in the GB connection queue?

    Ofgem's analysis puts data centres at about 73 GW of the demand connection queue, across around 315 projects ranging from 1 MW to 1,500 MW. Total contracted demand in the queue rose from 41 GW in November 2024 to 125 GW in June 2025. For scale, peak demand for the whole of Great Britain in 2025 was 45 GW.

    What is the proposed data centre commitment fee?

    Ofgem proposed that data centres of 40 MW and above connecting to the transmission system, or to distribution networks under a transmission assessment, secure a fee of about £237,500 to £712,500 per MW from accepting an offer until energisation. It is returned if the project proceeds as planned and forfeited if it terminates, cuts capacity or breaks the rules.

    Are Ofgem's data centre connection rules in force?

    Not as of 19 November 2026. Ofgem consulted on them from 29 July to mid-September 2026 and said it intends to decide later in 2026, then make the changes through industry codes, licences and contracts. Developers planning a connection now should design as if the milestones will apply, because the evidence takes months to prepare.

    Tags

    data centre grid connection ukofgem data centre connection reformdata centre commitment feedata centre queue milestonesdata centre connection queuelong lead electrical equipment data centredata centre demand connection

    Working on a project like this?

    Talk to our engineering team about your site, your grid connection or your power quality problem.

    Get in touch
    GET IN TOUCH

    Let's Solve Your Power Challenge.

    Send an enquiry to our engineering team. We'll help you identify risks and uncover efficiency opportunities.

    North America

    Renewable Energy & Drives

    5325 S Moorland RdNew Berlin, WI 53151United States

    UK & Europe

    Severn Drives & Energy

    Units 2 & 3, Kingsley Business ParkNew Road, Kibworth BeauchampLeicestershire, LE8 0LEUnited Kingdom

    Send an enquiry

    Fill out the form below and we'll be in touch.