Gate 2 offers are out: what a developer must do now, and by when
    Grid Technology

    Gate 2 offers are out: what a developer must do now, and by when

    Renewable Energy & Drives
    November 19, 2026

    Gate 2 Phase 1 offers were due by 31 October 2026 and distribution offers by 30 November. The deadlines that follow, and what to check before you sign.

    Quick answer

    Gate 2 Phase 1 offers were due by 31 October 2026, and distribution network operators are due to complete theirs by 30 November 2026. A transmission offer must be signed within 90 calendar days or it is withdrawn and replaced with a Gate 1 offer. Distribution offers set their own deadline, so check the letter.

    Key takeaways

    • Errors in a transmission offer must be raised within four weeks, and raising one does not stop the 90-day acceptance clock.
    • Signing commits you to security payments and to queue milestones; miss a milestone and the project can lose its place.
    • The offer letter usually triggers new study work (G99, power quality, protection), and some offers carry curtailment terms that change the business case.

    If you applied in the Gate 2 round of Britain's grid connections reform, the offer is on your desk or about to be, and a clock started the day it arrived. On a transmission offer you have 90 calendar days to sign and four weeks to query any errors, and an unsigned offer is withdrawn. Distribution offers set their own signing deadline, which the letter gives.

    This page is for anyone holding a Gate 2 offer, or waiting for one. It sets out the dates as they stand on 19 November 2026 and what to check in the offer, then the engineering work that usually follows. If you have the letter already, send it to us with your single-line diagram and an engineer from our UK studies team will tell you which studies it sets off.

    The Gate 2 timetable, as of 19 November 2026

    Ofgem confirmed the current timetable in a letter on 2 October 2026, after the system operator asked for a second extension to Phase 1.

    MilestoneDeadline
    Gate 2 Phase 1 offers issued by the system operator31 October 2026
    Phase 1 offers completed by the distribution network operators30 November 2026
    Gate 2 Phase 2 offers issued by the system operator31 January 2027
    Phase 2 offers completed by the distribution network operators31 March 2027

    The October extension covered about 62 offers, most of them waiting on construction offers from the transmission owner. Ofgem asked the system operator to confirm in writing once every Phase 1 offer had gone. We had not seen that confirmation by 19 November.

    These dates have moved twice already. Check the system operator's latest update before you plan around them.

    The acceptance clock, step by step

    The 90 days start when the offer arrives. Here is what happens inside them for a transmission offer issued by the system operator:

    1. Week 1, read the offer summary. Confirm the connection date, the point of connection, the capacity and the expiry date. Any of these may differ from what you applied for.
    2. By week 4, raise errors and change requests. Queries about mistakes in the offer have to be raised within four weeks of receiving it, and so do technical change requests. Raising a query does not pause the 90 days.
    3. By day 90, sign or lose it. The system operator says it cannot extend this period. The one exception is a four-week extension on re-issued offers that had material errors, and that depends on the transmission owner agreeing too.
    4. About 30 days after signing, put up security. Security is the financial guarantee against your share of the network works. The exact trigger and amount are in your offer documents.
    5. After signing, meet the queue milestones. Each project has dated milestones, such as securing land rights or planning consent. As one example from Ofgem, a project due to connect in two to three years has to meet the first milestone at least 18 months before its connection date. Miss one and you can lose the queue position you just secured.

    Distribution offers work differently. The system operator leaves the signing deadline to the network operator, so read the letter for the date and ask if it is not clear. Do not assume you have 90 days.

    What to check in the offer before you sign

    Most of the risk in a Gate 2 offer sits in the appendices. Go through these with your engineer and your lawyer together:

    • Connection date and point of connection. A different substation or voltage than you designed for can change the cable route, the transformer and the protection.
    • Works and costs. What is being built for you, who pays, and how the cost could move.
    • Security and liabilities. Check that the security matches your share of the works.
    • Curtailment and operational restrictions. Some offers let the network operator limit your import or export. Look for active network management terms in particular.
    • Technical requirements. The performance the network operator expects from your plant at the connection point.
    • Milestones. Make sure the project can meet every one, including the ones you have already passed, such as planning.

    If the connection date in the offer does not work for the project at all, the comparison in our article on grid connection queue delays and private wires shows where a direct supply to a nearby user can step in.

    What the offer says about curtailment

    Read the curtailment terms twice. Many new connections in Britain come with active network management conditions. These let the network operator turn your site down, or off, when the local network is under strain. The condition sits in your connection terms, and the operator does not have to ask you on the day.

    That is a fair trade for getting connected sooner. But if your finance model assumes a fixed volume of exports every year, every curtailed hour comes straight off revenue, and you decide neither when it happens nor how often. Model it before you sign, using the hours or limits stated in the offer.

    If you are unsure what the curtailment terms in your offer mean in hours and pounds, send the offer and the site's expected output profile to sales@severnde.co.uk and an engineer will tell you which figures in it to model first.

    The studies a Gate 2 offer usually sets off

    Signing the offer starts the engineering work. A distribution-connected generation or battery site will normally need:

    • G99 compliance studies. G99 is the GB rulebook for connecting generation and storage to the distribution network, and the studies show your plant meets it at the point of connection in the offer.
    • Power quality assessments: harmonics (waveform distortion from inverters and drives) under G5/5, and voltage step changes, such as transformer switching, under P28.
    • Protection and earthing design for the agreed point of connection.
    • Fault level checks, so new and existing switchgear can safely handle a short circuit.

    A changed point of connection can mean redoing studies you thought were finished. Our page on UK grid connection engineering explains each study in plain terms, and why grid connection projects get delayed covers the usual causes of slippage after the offer.

    If you get a Gate 1 offer instead

    A Gate 1 offer is a holding position. It carries no firm connection date and no confirmed point of connection, and the project has to wait for a later application window to try for Gate 2 again. The same happens if you let a Gate 2 offer lapse, and the system operator warns that the replacement Gate 1 offer can take longer to arrive because Gate 2 offers come first.

    If that leaves the project without a workable date, it is time to look at other routes: a smaller or phased connection, storage to cut the peak, or a private wire to a user nearby. Our GridLink private wire page explains how a direct supply can work alongside a grid connection.

    What to do this week

    1. Find the expiry date on your offer and put the 90-day (or the network operator's) deadline and the four-week query deadline in the diary.
    2. Check the point of connection and the curtailment terms against your design and your finance model.
    3. List the studies the offer triggers, and book them now. Study work is often what holds up the next milestone.

    Holding a Gate 2 offer and not sure what it commits you to? Our UK team at Severn Drives & Energy in Kibworth, Leicestershire, runs the grid connection studies a connection offer sets off: G99, power quality, protection and fault level. Send us the offer letter and your single-line diagram, and an engineer will tell you which studies it triggers and what to check before you sign. Send an enquiry, email sales@severnde.co.uk (UK) or sales@renewable-d.com (US), or call +44 116 279 6131 (UK) or +1 414 562 6559 (US). More about the UK team is on the Severn Drives & Energy page.

    Frequently asked questions

    How long do I have to accept a Gate 2 connection offer?

    For an offer issued by the system operator for a transmission connection, 90 calendar days, and that period cannot be extended except for a short extension on re-issued offers with material errors. If you do not sign, the offer is withdrawn and you are given a Gate 1 offer instead. Distribution offers state their own deadline in the letter, so check it the day it arrives.

    What happens if I do not accept my Gate 2 offer?

    The Gate 2 offer is rescinded and the project is re-offered a Gate 1 agreement, which carries no firm connection date or point of connection. The system operator warns that a replacement Gate 1 offer can take longer to arrive, because Gate 2 offers are being prioritised. The project then waits for a later application window.

    When are Gate 2 Phase 2 offers due?

    Under the timetable Ofgem confirmed on 2 October 2026, Phase 2 offers are due from the system operator by 31 January 2027, and distribution network operators are expected to complete their Phase 2 offers by 31 March 2027. These dates have already moved twice for Phase 1, so check the latest system operator update.

    Tags

    gate 2 connection offergate 2 offer acceptancegate 2 phase 1 offersgate 2 phase 2 offersgate 2 offer deadlineconnections reform offergate 1 offer

    Working on a project like this?

    Talk to our engineering team about your site, your grid connection or your power quality problem.

    Get in touch
    GET IN TOUCH

    Let's Solve Your Power Challenge.

    Send an enquiry to our engineering team. We'll help you identify risks and uncover efficiency opportunities.

    North America

    Renewable Energy & Drives

    5325 S Moorland RdNew Berlin, WI 53151United States

    UK & Europe

    Severn Drives & Energy

    Units 2 & 3, Kingsley Business ParkNew Road, Kibworth BeauchampLeicestershire, LE8 0LEUnited Kingdom

    Send an enquiry

    Fill out the form below and we'll be in touch.