Rebuilding a burned-out DSTATCOM inverter on site
    Grid Technology

    Rebuilding a burned-out DSTATCOM inverter on site

    Pedro Salvestro
    August 11, 2026

    An arc fault destroyed a DSTATCOM inverter section. Instead of shipping it to a factory, we rebuilt it on site from the drawings up. How the job was done.

    Quick answer

    A burned-out DSTATCOM inverter section can be rebuilt on site if its frame is sound and the drawings exist. After an arc fault destroyed one section, we stripped it to the frame, dry ice cleaned it, reordered every part including custom bus bars, and rebuilt it in place in about a month. It came back online with no issues.

    Key takeaways

    • Sending the section to a factory would have meant removing seven healthy inverters to reach it, then putting all seven back months later.
    • The whole section was lost to one loose connection on a breaker, which arced and caught fire.
    • The rebuild was the last step of a fleet refurbishment that had already taken the DSTATCOMs from about half their rated output to about 90 percent.

    When a fire guts one section of a DSTATCOM (a power electronics unit that holds the voltage steady on a distribution network), the usual advice is to pull the section out and ship it to a factory. If the frame is still sound and the original drawings exist, it can be stripped and rebuilt where it stands instead, which matters most when healthy equipment is in the way. We did that for a utility customer after an arc fault burned one section from top to bottom, and the rebuilt inverter came back online with no issues. If you have a damaged section now, send us photos of the damage and the nameplate and we will tell you whether an on-site rebuild is realistic.

    This page is for utilities and site owners who run DSTATCOMs and STATCOMs and are looking at a damaged section. It walks through what failed, why the factory route made no sense on that site, how the section was rebuilt and when an on-site rebuild is the wrong call. For the wider service, see our STATCOM repair and service page.

    What failed: one loose breaker connection

    It started with a loose connection on a breaker. The joint arced, the arc caught fire, and the fire took out an entire inverter section of the customer's DSTATCOM from top to bottom. That section held two inverters built together, the AC breakers and hundreds of supporting parts. Most of it was trashed.

    A DSTATCOM (distribution static compensator) is a power electronics system that pushes reactive power into a distribution network, or pulls it out, to hold the voltage steady; our article on how a DSTATCOM stops voltage sags explains the job it does. Each section is a dense assembly. It holds the semiconductor stacks that do the switching, plus capacitors, breakers, custom bus bars and even glass insulators. If yours is a PureWave unit, our PureWave DSTATCOM support page covers spares and board repair for that line.

    The fleet was already at 90 percent

    The customer had brought us in to refurbish an ageing fleet of DSTATCOMs that years of service had left at about half its rated output, and our refurbishment work brought it back to about 90 percent. The last stretch came down to one inverter. It was the one that burned.

    Why the factory route made no sense on this site

    Getting the damaged section to a factory would have meant removing seven healthy inverters first. The usual repair for damage like this is to disconnect the whole section and ship it back for a factory rebuild, because rebuilding one in the field is hard and many service teams will not attempt it. On this site, though, the burned inverter sat at the back of a lineup with seven working inverters in front of it. All seven would have had to come out, and then go back in when the section returned months later.

    That plan fails on cost, on risk and on time.

    Factory rebuildOn-site rebuild
    Healthy inverters disturbedSeven removed, then reinstalledNone
    Risk to working equipmentEvery disconnection and reconnection is a chance to introduce a new faultWork stays inside the damaged section
    Output while the work is doneReduced for the whole round trip, monthsReduced for the rebuild only, about a month
    What you pay forThe factory rebuild, plus removing and refitting seven invertersParts, remanufactured bus bars and site labour

    So we did the difficult thing and rebuilt it at component level, in place.

    If a damaged section on your site is boxed in by healthy equipment, send photos of the damage and the nameplate to sales@renewable-d.com (US) or sales@severnde.co.uk (UK), and we will tell you whether it can be rebuilt where it stands.

    How the section was rebuilt

    1. Strip-out. Every damaged component came out until only the frame was left. A space that normally holds hundreds of parts was completely empty.
    2. Cleaning. Fire leaves conductive soot and debris on every surface. The section was dry ice blasted, which lifts the contamination without moisture or abrasive residue. That matters when the same surfaces will carry medium voltage equipment again.
    3. Parts. We went through the original drawings line by line and ordered everything the rebuild needed, from capacitors and breakers down to nuts, bolts and insulators. The bus bars were the awkward part. You can't just pick them up, because they are custom made for the application. They were remanufactured to the drawings.
    4. Build. With the parts on site, the team assembled the section from scratch in place: bus work, wiring, breakers and power stages.
    5. Return to service. The rebuilt inverter was tested, energised and brought back online. It started without any issues and has run without them since, and the fleet got its final stretch of capacity back.

    End to end, the job took about a month.

    When an on-site rebuild is the wrong call

    Fire damage looks terminal, and a factory return was the established answer, but neither of those decided this job. The section was repairable because the frame was sound, the design was documented, and every damaged part could be identified and either ordered or remade.

    Take one of those away and the answer changes. A frame that is distorted or cracked, drawings that are missing with no way to remake the custom parts, or damage that has spread into sections meant to stay in service points toward a factory repair or, in the worst case, replacement. Once we have seen the photos, we will say whether an on-site rebuild is viable. Buying new is rarely quicker, though: transformer and switchgear lead times alone can run past two years.

    A failure that looks like an equipment defect can also come from the supply. When that is in doubt, power quality root cause analysis comes before anyone spends money on parts.

    What drives the cost of an on-site rebuild

    The cost depends on how much of the section has to be replaced, how many custom parts such as bus bars must be remanufactured, how long the team needs on site, and how much testing the network operator needs before the unit goes back into service. Most of that is visible in the photos and the drawings, which is why we ask for them first.

    What to do next

    1. Photograph the damage before anything is moved, from the front and from inside the section if it is safe to open.
    2. Photograph the nameplate and note the model, rating and roughly when the unit was installed.
    3. Send both with the event or alarm log from the time of the fault, and tell us whether you still have the original drawings. The drawings decide a lot.

    Damaged or burned-out inverter section? We rebuild DSTATCOM and STATCOM sections on site from the original drawings, remanufactured bus bars included, so healthy equipment stays where it is. Send photos of the damage and the nameplate, and we will tell you whether an on-site rebuild is viable and roughly what it would involve. Send an enquiry, email sales@renewable-d.com (US) or sales@severnde.co.uk (UK), or call +1 414 562 6559 (US) or +44 116 279 6131 (UK).

    Frequently asked questions

    Can a burned-out DSTATCOM inverter section be rebuilt on site?

    Yes, when the frame is structurally sound and the original drawings are available. The section is stripped to the frame, cleaned, and rebuilt to the original design with every damaged part replaced, including custom bus bars remanufactured from the drawings. It is demanding work, but it avoids removing healthy equipment just to get the damaged section out.

    When is an on-site rebuild better than a factory repair?

    When access is the problem. If reaching the damaged section means removing healthy equipment around it, the factory route adds the cost of removal and reinstallation, months of reduced output, and the risk of new faults in equipment that was working. An on-site rebuild keeps the work inside the section that failed.

    What is a DSTATCOM?

    A DSTATCOM, or distribution static compensator, is a power electronics system connected to a distribution network that injects or absorbs reactive power to hold the voltage steady. Utilities and industrial sites use them to correct voltage sags and flicker, and wind farms use them to meet grid code requirements at their connection point.

    Tags

    dstatcom repairstatcom repairinverter rebuildon-site power electronics repairarc flash damage repair

    Working on a project like this?

    Talk to our engineering team about your site, your grid connection or your power quality problem.

    Get in touch
    GET IN TOUCH

    Let's Solve Your Power Challenge.

    Send an enquiry to our engineering team. We'll help you identify risks and uncover efficiency opportunities.

    North America

    Renewable Energy & Drives

    5325 S Moorland RdNew Berlin, WI 53151United States

    UK & Europe

    Severn Drives & Energy

    Units 2 & 3, Kingsley Business ParkNew Road, Kibworth BeauchampLeicestershire, LE8 0LEUnited Kingdom

    Send an enquiry

    Fill out the form below and we'll be in touch.