Before you sign a private wire PPA: seven engineering questions
    Grid Technology

    Before you sign a private wire PPA: seven engineering questions

    Renewable Energy & Drives
    November 19, 2026

    A private wire PPA fixes the price, but the engineering decides whether the power arrives. Seven questions for the network, metering, faults and upkeep.

    Quick answer

    A private wire PPA is a long-term contract for power delivered over a dedicated cable from a generator to a nearby user. Before signing, settle seven engineering points: backup supply, network operator approval, fault protection, metering and losses, power quality, what happens to surplus power, and who maintains the cable. Each one changes what the contract needs to say.

    Key takeaways

    • The network operator has to agree the scheme even if no power will ever be exported, because the generator runs in parallel with the public network.
    • The meter's position decides who pays for the energy lost in the cable between the two sites.
    • A private cable is not on the statutory records contractors search before digging, so the owner has to make it findable.

    You have heads of terms for a private wire PPA in front of you: a long-term deal for power from a nearby solar or wind farm, delivered over a cable that never touches the public network. The commercial terms get most of the attention: the price, the length, the volume the buyer must take. Richard, who runs our UK business development, puts the appeal simply: a solar site next door is far more forecastable than the market, and "It takes the volatility out of the pricing." The engineering decides whether that price ever turns into delivered power.

    This page is for landowners, generators and the businesses buying from them. It sets out seven engineering questions to settle before the contract is signed, because each one changes what the contract needs to say. If you are new to the idea, our explainer on what a private wire is covers the basics. If you already have draft terms, send us the two sites and the draft and we will tell you which of the seven are still open.

    1. What supplies the site when the generator is not producing?

    The user's own grid connection does. So that connection stays, and it has to be big enough for the site's full demand. Solar produces nothing at night and little on a December afternoon. Wind drops for days. The buyer still needs power from a licensed supplier for those hours.

    Two things follow for the contract. The grid supply contract has to cope with large swings in how much grid power the site takes, without volume penalties. And the PPA should say what happens when the generator is offline for maintenance, so nobody argues later about who pays for the replacement power.

    2. Does the network operator have to approve it, and what happens to the existing connection?

    Yes. If the generator can run in parallel with the public network, the network operator has to issue a connection offer for it, even if no power will ever be exported. That cost normally falls to the generator, and which party holds the agreement is a point to settle in the PPA.

    The usual arrangement keeps the grid connection at the user's site, so the user's supply and billing stay separate. If the connection point ends up at the generator instead, the network operator may treat the generator as the supplier for everything the user takes, including grid top-up. That puts far more risk on the generator. Two separate grid connection points joined by a private wire are rare, and the protection needed to make them safe is expensive.

    A plain direct wire normally needs a hard changeover, so the user's site runs on one supply or the other, never both at once. A converter-based private wire such as our GridLink system controls how much power flows and keeps it flowing one way, from the generator to the site, so the site can keep its grid connection and take private wire power alongside it.

    3. What happens when there is a fault on the wire or at either site?

    Protection has to clear it without anyone getting hurt or either site losing supply unnecessarily. Joining a generator to a grid-connected site creates two risks. Back-feed is the first: power from the generator flowing into a public network that engineers believe is switched off. The second is a parallel path, where power circulates between the two connection points and the relays on either site misread what they see.

    The scheme needs a protection design that covers the cable, both ends and the interface with each grid connection, with earthing to match.

    This is the part a network operator will look at hardest.

    Our page on protection coordination for grid connections explains how relays are set so the right breaker trips first.

    4. Where is the power metered, and who carries the losses?

    The meter decides who pays for what.

    Some energy is always lost as heat along the cable and in the transformers. If the meter sits at the generator, the buyer pays for energy it never receives. If it sits at the buyer's end, the generator carries those losses, and over a long cable at a modest voltage that can be enough to matter in a price negotiated to fractions of a penny.

    The scheme needs a meter that can measure what the generator exports, installed by a meter operator, in a location both parties accept. A meter housing may need building at either site. None of this is quick. Agree the position, the accuracy class and who reads it before the PPA is signed, because the price per unit only means something once both sides agree what a unit is.

    5. Who is responsible for power quality at the point of delivery?

    The PPA should name a party. The design should then give that party the means to meet it. Inverters on a solar or battery site produce harmonics, which are distortions of the electrical waveform. Long cables affect voltage at the far end. If the buyer's equipment trips, or the network operator finds the combined site breaches its harmonic limits, someone has to fix it. Studies at design stage show whether filtering or voltage control is needed. GridLink controls voltage and power quality at the point of connection as part of how it works. With a plain wire, it is a separate design job. Our guide to harmonic filters is a plain-language introduction.

    6. What happens to power the user cannot take?

    It is exported, curtailed or stored. Each has a cost. Factories close at weekends. Cold stores have quiet nights. A solar farm on a June Sunday can produce far more than the buyer needs.

    If the generator has export capacity, the surplus goes to the grid at the export price, subject to any curtailment terms in its own connection offer. If export capacity is not available at a sensible price, the scheme has to be sized to the buyer's demand, or a battery added. On the buyer's side, most PPAs include a take-or-pay clause for a minimum volume, so the generator can finance the project. The engineering numbers (the hour-by-hour match between output and demand) are what make that minimum fair.

    The size of the saving also depends on where you are, because the network charges a private wire avoids are set region by region.

    7. Who owns, operates and maintains the cable, and how fast is a fault fixed?

    Decide this before anything is built. A private cable needs a control, operation and maintenance agreement with a qualified high voltage contractor who is on call for faults, with agreed response and repair times. The PPA should say who owns the cable and the equipment at each end, who insures them, and who pays when they fail.

    There is a trap here that catches owners out. A network operator's cables show up on the search services contractors check before digging. A private cable does not, unless the owner registers it.

    Cable strikes can kill. Register the route.

    The route also needs consents of its own. Network operators install cables under statutory powers that a private wire does not have, so planning consent and agreements with every landowner along the route are the developer's job.

    The seven questions, and what each changes in the PPA

    QuestionWhat it changes in the contract
    Backup supplyBuyer keeps a full-size grid supply with no volume penalties; outage terms
    Network approval and connection pointWho applies, who holds the agreement, who pays
    Fault protectionProtection design signed off before construction; who owns each relay
    Metering and lossesMeter position, accuracy and who reads it
    Power qualityNamed responsibility and limits at the delivery point
    Surplus powerExport, curtailment or storage; the take-or-pay minimum
    Ownership and maintenanceMaintenance contract, repair times, insurance, cable records

    What to do before the heads of terms become a contract

    1. Put an engineer in the room while the commercial terms are still moving.
    2. Build the hour-by-hour match between the generator's output and the buyer's demand. It answers questions 1 and 6 at once.
    3. Open the conversation with the network operator early. Its answer on question 2 can change the design and the price. Our article on grid connection queue delays and private wires shows why waiting for the network is often what a private wire avoids.

    Negotiating a private wire PPA and want the engineering settled first? We design private wire connections and supply GridLink, a converter-based private wire that lets the buyer's site keep its grid connection alongside the private supply. Send us the two sites, the distance between them and the draft heads of terms, and we will tell you which of these seven questions are still open and what would answer them. Send an enquiry, email sales@severnde.co.uk (UK) or sales@renewable-d.com (US), or call +44 116 279 6131 (UK) or +1 414 562 6559 (US).

    Frequently asked questions

    Does a private wire need network operator approval?

    Yes, in almost every case. If the generator can run in parallel with the public network, the network operator has to issue a connection offer for it, even where no power is exported. The operator reviews protection on both sites and how the private wire sits with each grid connection. Start that conversation alongside the commercial talks, not after the PPA is signed.

    What happens when the generator is not producing?

    The user's site takes the rest of its power from its own grid supply, so a private wire user almost always keeps a grid connection sized for its full demand. The grid supply contract should be flexible enough to cope with the swings. A plain direct wire usually needs a changeover between the two supplies; a converter-based link can share the load without one.

    Who maintains a private wire?

    Whoever owns it, normally through a control, operation and maintenance agreement with a qualified high voltage contractor who is on call for faults under agreed service levels. The PPA should say who owns the cable and the equipment at each end, who insures them, who pays for repairs, and how quickly a fault must be fixed.

    Tags

    private wire PPAprivate wire agreementprivate wire connection requirementsprivate wire DNO approvalprivate wire meteringprivate wire maintenanceprivate wire power purchase agreement

    Working on a project like this?

    Talk to our engineering team about your site, your grid connection or your power quality problem.

    Get in touch
    GET IN TOUCH

    Let's Solve Your Power Challenge.

    Send an enquiry to our engineering team. We'll help you identify risks and uncover efficiency opportunities.

    North America

    Renewable Energy & Drives

    5325 S Moorland RdNew Berlin, WI 53151United States

    UK & Europe

    Severn Drives & Energy

    Units 2 & 3, Kingsley Business ParkNew Road, Kibworth BeauchampLeicestershire, LE8 0LEUnited Kingdom

    Send an enquiry

    Fill out the form below and we'll be in touch.