What is a private wire? Connecting local generation directly to local demand
    Grid Technology

    What is a private wire? Connecting local generation directly to local demand

    Raveenthan Thambirajah
    August 11, 2026

    A private wire takes a generator's power straight to a nearby user. How private wire networks and private grids work, what they need, and who builds them.

    Quick answer

    A private wire is a dedicated cable that carries electricity from a generator, such as a solar farm, straight to a nearby user, such as a factory, without using the public network. It can run alone (islanded) or alongside the user's grid connection. The cable route, land rights and power contract usually set the cost and timetable.

    Key takeaways

    • As one example, a publicly funded Scottish advice service puts a 1 km private wire at around £250,000 all in, with about £120 a metre assumed for the cable and its trench.
    • In Great Britain the seller needs a supply licence or an exemption; the small-supplier exemption caps supply at 5 MW, no more than 2.5 MW of it to homes.
    • A site that switches between the private wire and the grid needs a fail-safe changeover so the two are never connected at once; a dual connection runs them in parallel with the flow controlled.

    A private wire is a dedicated cable that takes electricity from a generator straight to a nearby user. A solar farm on one side of the fence feeds the factory on the other, and the power never enters the public network. The factory gets a known price for its energy. The farm gets a better price than it would for export. If you have a generator and a large user within reach of each other, send us the two sites and your figures and we will tell you if a private wire looks feasible.

    Most people in energy know private wires exist. Ask how one gets built and the answers thin out. This page covers the build, the cost, the timetable and who does the work, for landowners, developers, and plant or estate managers weighing one up.

    What a private wire is

    A private wire connects local generation to local demand over a cable that belongs to the private arrangement, not to the network operator. Instead of exporting every unit to the grid while the user buys power back through a supplier, the generator sends part or all of its output directly to the user.

    There are two ways to run one. In islanded operation the private wire is the user's only supply and the public grid is not involved. In a dual connection the private wire runs alongside the user's existing grid connection. The flow from the generator is set and controlled. The grid supplies whatever the private wire does not.

    In the US the nearest term is behind-the-meter power, which means generation connected on the customer's side of the utility meter.

    Private wire networks and private grids

    A private wire network is the same idea with more than two parties. Several generators, several users, or both, share dedicated cables: an industrial estate fed by a solar farm and a battery, say, or a group of buildings sharing one generation site. Some people call this a private grid.

    The questions stay the same as for a single wire. There are just more of them. Power flow has to be managed on every branch. Protection has to work for every mix of sources, and the metering has to show what each party supplied and took.

    Why both sides want one

    For the generator, selling to a neighbour pays more per unit than selling to the grid. The user pays less per unit than for grid supply, because the power is not carrying all the network charges that grid electricity does.

    Price certainty matters as much as price. A business on a private wire knows what its energy will cost, and it can plan around that even if market prices later fall. It takes the volatility out of the pricing.

    For a site stuck in a long queue for more grid capacity, a private wire can also be the quickest route to the power it needs. We cover that case in grid connection queue delays and when a private wire is the better answer.

    How a private wire gets built, step by step

    The electrical design is only one part of the job, and on most schemes it is not the slowest. A typical private wire goes through these stages, and several of them run at the same time:

    1. Feasibility. Compare the generator's output with the user's demand through the day and the year. A 10 MW solar farm cannot simply supply a site that needs 10 MW at night. Check the distance and the likely cable route.
    2. Route and land. Agree a cable route, and get wayleaves (permission to lay and keep a cable on land you do not own) from every landowner along it. Crossing a road, a railway or a river can decide whether a route works at all.
    3. Contract and licence. The generator and user sign a long-term power purchase agreement, which sets the price, the term and what happens if either side stops. In Great Britain the seller also needs a supply licence or a licence exemption. The small-supplier exemption caps supply at 5 MW, of which no more than 2.5 MW can go to homes. Take legal advice on this early.
    4. Network operator. If the user keeps a grid connection, the local network operator has to approve how the two supplies sit together. A switched arrangement, where the site runs on one supply at a time, needs a fail-safe changeover so the two can never be connected at once.
    5. Design. Size the cable and switchgear. Set the protection so faults clear correctly on both sides (see what protection coordination involves). Control voltage and power flow where the wire meets the user's site, and fit metering both parties trust.
    6. Build, test and energise. Lay the cable, install the switchgear and control equipment, and run the tests the network operator wants to witness before the link goes live.

    If you are at step 1 or 2, talk to an engineer now. Email both sites, the distance between them and whatever generation or demand figures you have to sales@severnde.co.uk (UK) or sales@renewable-d.com (US). We will tell you whether a private wire looks feasible, and which step is likely to decide it.

    How much does a private wire cost?

    Distance and ground set most of the price. A private wire across one field is a different job from one that has to follow a road for two kilometres, cross a railway and pass through several farms.

    One published UK example gives a sense of scale. A worked example from a publicly funded Scottish advice service puts a 1 km private wire at around £250,000 in total. Cable and trenching account for about £120,000 of that (roughly £40 a metre for cable and £30 to £50 a metre to dig soft ground, rising to £90 to £120 a metre under roads). The rest covers switchgear, a transformer, a switchroom with ring main units at each end, an export meter, design and surveys, legal work and a 20% contingency. Treat that as an example of how the total builds up, not as a quote and not as our price, because the voltages on each side, the length of the route and the layout of the two sites can each move it a long way.

    Cost driverWhy it moves the price
    DistanceCable and trenching are charged by the metre
    Ground and crossingsRoads, rail and rivers cost far more to cross than open fields
    WayleavesLegal fees and rental payments to each landowner on the route
    VoltageA transformer is needed if the generator and user run at different voltages
    Keeping the grid connectionAdds changeover or converter equipment, protection work and the network operator's review
    ContractA long-term power purchase agreement needs proper legal work on both sides

    The same source notes that a private wire can cost as much as a standard grid connection or more, and that generator and user can split the bill. Routes get longer on bigger schemes, where the scale can absorb more of the cable cost.

    How long does a private wire take?

    Longer than most people expect. The equipment is rarely the reason. Getting wayleaves from every landowner on the route takes time, and so do planning consent and a long-term power contract both sides are willing to sign. On larger schemes, contract negotiation and planning alone can take several years. Starting the engineering, the land work and the legal work together, instead of one after the other, is the biggest saving you can make. Grid connection projects run late for reasons that apply here too; we list them in why grid connection projects get delayed.

    Private wires are built by power engineering firms. The firm has to design the connection, supply the power electronics, set the protection and commission the link to the network operator's rules. Not many do all of it.

    The awkward part is the user's existing grid connection. Without control, a direct wire between a generator and a grid-connected site risks feeding power back into the public network. One answer is a switched arrangement: a changeover drops one supply before the other can connect, so the site runs on one or the other. The other answer is a dual connection, with both running in parallel and the power flow controlled.

    GridLink, our private wire system, is built around a power electronics converter that regulates active power flow from generator to user. It prevents unintended export outside the private connection, and it provides the reactive power control that holds voltage steady across the connection. In a dual connection the user keeps the grid connection, takes private wire power alongside it, and the grid supplies the rest. The network operator still reviews the design.

    GridLink ships as a modular, factory-assembled outdoor unit that sits next to existing high voltage equipment. It runs islanded or alongside the grid, and it can be adapted to different network voltages, generation technologies and loads. More detail is on our GridLink private wire page.

    If you are buying a solar farm that already has a private wire attached, the same questions belong in your technical due diligence when a solar farm changes hands.

    What to do next

    1. Map the two sites. Note the distance and the likely cable route, and mark every crossing and every landowner along it.
    2. Put the profiles side by side. Compare the generator's output with the user's demand hour by hour, so you know how much the private wire will carry and how much the grid still has to supply.
    3. Decide about the grid connection. Choose whether the user keeps it, because that decides the equipment, the network operator's involvement and part of the cost.

    Weighing up a private wire between a generator and a site that needs the power? GridLink, our converter-based private wire system, can run islanded or in parallel with a site's grid connection. Send us the two sites, the distance between them and the demand or generation figures, and we will tell you whether it looks feasible and what would decide it. Send an enquiry, email sales@severnde.co.uk (UK) or sales@renewable-d.com (US), or call +44 116 279 6131 (UK) or +1 414 562 6559 (US).

    Frequently asked questions

    What is a private wire connection?

    A private wire connection is a dedicated cable that delivers power from a generator directly to a nearby user instead of through the public grid. It can run islanded from the grid or in parallel with the user's existing grid connection. In both cases the amount of power that flows, and where it is allowed to go, has to be controlled and metered at the point of connection.

    How much does a private wire electricity connection cost?

    It depends mostly on distance and ground. As one example, a publicly funded Scottish advice service puts a 1 km private wire at around £250,000, assuming about £120 a metre for cable and trenching, and more where the route runs under roads. Switchgear, metering, a transformer if the voltages differ, design, legal work and contingency make up the rest. A site survey turns that into a real number.

    How long does a private wire take?

    The electrical equipment is rarely the slow part. The time goes on the cable route, land rights and wayleaves, planning, the long-term power contract and, where the user keeps a grid connection, the network operator's review. On larger schemes, contract negotiation and planning alone can take several years. Starting the engineering and the legal work in parallel saves the most time.

    Tags

    what is a private wireprivate wire connectionprivate wire electricityprivate wire powerbehind the meter powerconnecting generation directly to demand

    Working on a project like this?

    Talk to our engineering team about your site, your grid connection or your power quality problem.

    Get in touch
    GET IN TOUCH

    Let's Solve Your Power Challenge.

    Send an enquiry to our engineering team. We'll help you identify risks and uncover efficiency opportunities.

    North America

    Renewable Energy & Drives

    5325 S Moorland RdNew Berlin, WI 53151United States

    UK & Europe

    Severn Drives & Energy

    Units 2 & 3, Kingsley Business ParkNew Road, Kibworth BeauchampLeicestershire, LE8 0LEUnited Kingdom

    Send an enquiry

    Fill out the form below and we'll be in touch.