Buying or refinancing a solar farm? The studies to redo first
    Grid Technology

    Buying or refinancing a solar farm? The studies to redo first

    Raveenthan Thambirajah
    August 11, 2026

    Buying or refinancing a working solar farm? The engineering studies to redo before the sale completes, and why the seller's paperwork is not enough.

    Quick answer

    Before buying or refinancing an operating solar farm, have an engineer check five things: that the compliance paperwork is complete, that the site still meets the grid rules it was approved under (G99 in Great Britain), that the protection settings match what the network operator approved, that power quality is inside its limits, and that the site matches its drawings.

    Key takeaways

    • The connection agreement and its obligations pass to the new owner with the site, so any gap in the compliance evidence becomes the buyer's problem after completion.
    • Inverter swaps, string changes and firmware updates since commissioning can all move a site away from the performance its original studies describe.
    • In the UK the power quality evidence has three named studies to ask for: a G5/5 harmonic assessment, a P28 voltage flicker study and a P29 voltage unbalance study.

    You are about to buy an operating solar farm, or lend against one, and the seller has handed over a folder of studies and test certificates. Before the deal completes, have an engineer check that the folder still describes the site: its grid performance, its protection settings and its power quality as they are today, not as they were on the day it was switched on. A problem found before completion can go into the price. Found after, it is yours.

    Most solar farms are built by one company and owned by another. A developer takes the site through planning, the grid connection and construction, then sells the finished farm to an investor and moves on to the next one. Every sale, and every refinancing, raises the same question for the new owner or lender: is the site compliant, and does it perform the way the seller's paperwork says? The checks that answer it are called technical due diligence. We do a lot of this work, and this page sets out what it involves.

    If you have a deal in progress, send us the list of documents the seller has provided and an engineer will tell you which studies are missing. Our UK power system studies team runs these checks for buyers.

    What you take on when you buy a solar farm

    You are buying more than panels and land. A grid-connected solar farm in Great Britain runs under a connection agreement with the local distribution network operator (the DNO, the company that runs the local network). Behind that agreement sits a stack of technical evidence. There are studies showing the site meets G99, the engineering rules for generators connecting to distribution networks. There are protection settings the DNO approved. And there are the test results from the day the site was commissioned.

    All of that passes to you with the site, and so does the responsibility for it. If a compliance question comes up two years after you buy, the developer has gone and the question is yours.

    Why the seller's paperwork may not match the site

    Three things tend to slip between the day a site is commissioned and the day it is sold.

    The paperwork is incomplete. Commissioning records, study files and as-built drawings often arrive with gaps, and what the seller hands over does not always match what the DNO has on file.

    The site has changed. Inverters get swapped, strings get reconfigured and firmware gets updated, and any of those can move the site away from the performance its original studies described.

    The people have gone. The engineers who made the design decisions left with the developer, and nobody on the buying side was in the room when they were made.

    The five checks to commission before completion

    CheckWhat it answersWhat tends to go wrong
    Paperwork reviewDo the studies and test records the connection agreement requires exist, and do they match the DNO's file?Missing commissioning records; drawings that predate later changes
    Grid compliance checkDoes the site still control voltage, respond to frequency, ride through faults and manage reactive power the way its approved studies say?Inverter or firmware changes that were never re-studied
    Protection checkDo the relay settings on site match the schedule the DNO approved?Settings changed on site and never sent back for approval
    Power quality checkAre harmonics, flicker and unbalance inside the agreed limits, measured now?Replacement inverters with different harmonic behaviour
    Site walk-downDoes the site physically match the as-built drawings?Undocumented modifications

    The paperwork review is desk work and comes first, because it decides how much of the rest you need. The grid compliance check models the site using the same kind of simulation the original connection studies should have used. The protection check compares what is set in each relay with what was approved; protection coordination is one of the places where site and paperwork most often drift apart.

    The power quality check has formal names in the UK, and you should ask the seller for each one. A G5/5 harmonic assessment covers harmonics, the distortion that inverters add to the network's voltage (see what harmonic filters do). A P28 study covers voltage flicker, the rapid voltage changes that make lights flicker for neighbours. A P29 study covers voltage unbalance between the three phases. If the site has changed since they were done, have them re-run against fresh measurements. Where a measurement comes back wrong and the cause is not obvious, power quality root cause analysis separates a site problem from a network one.

    If you are part way through a purchase and the seller's pack looks thin, send us the document list and the connection agreement at sales@severnde.co.uk (UK) or sales@renewable-d.com (US) and an engineer will tell you which of these five checks it supports and which it does not.

    Is a re-study required by law when a solar farm is sold?

    Whether a formal re-study is required at the point of sale depends on the agreements involved, and it varies case by case. What does not vary is where the problem lands. The connection agreement's obligations travel with the site, lenders and insurers increasingly want current technical evidence instead of inherited paperwork, and any warranty claim against the seller is limited by the terms of the sale.

    If you are refinancing

    The lender's technical adviser will usually want the same evidence a buyer does, because the lender is taking on the same risk. So the same five checks apply. Tell us what the lender has asked for and we will say whether we can help.

    When the checks turn something up

    Sometimes the site was not designed right in the first place. Our consultancy team has worked on sites that needed real remedial engineering before they were properly compliant. Those problems did not stop the original commissioning. They surfaced later, under a new owner, at the worst possible time. Found during due diligence, the same problem becomes something you can negotiate: a price adjustment, an obligation on the seller, or a planned fix with a cost attached. New connections show the same pattern, as set out in why grid connection projects get delayed.

    Much of what turns up can be fixed without replacing equipment. A drifted relay setting usually means resetting the relay and sending the corrected schedule back to the DNO. An inverter that has fallen out of its approved behaviour can usually be reset, repaired or re-studied. Replacement is the answer only when the measurements say so. And if the new owner's people will be working on live equipment, this is also the moment to commission an arc flash study, since the duty to manage that risk sits with whoever runs the site.

    What we need from you

    1. The list of documents the seller has provided.
    2. The connection agreement and the original connection offer.
    3. The last compliance reports: G99 studies, and the G5/5, P28 and P29 studies if they exist.
    4. The protection settings schedule and the single line diagram.
    5. Commissioning test records, and a list of any equipment changes since commissioning.

    What to do next

    1. Ask the seller for the five items above before you agree the timetable, not after.
    2. Have the paperwork reviewed first. It tells you which of the other checks you need and how long they will take.
    3. Get any gap priced, fixed or written into the contract as the seller's problem before you sign.

    Buying or refinancing a solar farm? Our UK consultancy team runs the paperwork review, grid compliance, protection and power quality checks for buyers, and tells you plainly which gaps matter and which do not. Send the seller's document list and the connection agreement, and an engineer will tell you which studies are missing. Send an enquiry, email sales@severnde.co.uk (UK) or sales@renewable-d.com (US), or call +44 116 279 6131 (UK) or +1 414 562 6559 (US).

    Frequently asked questions

    What is technical due diligence for a solar farm?

    It is an independent engineering check of an operating solar farm before someone buys it or lends against it. An engineer reviews the grid connection paperwork, the protection settings, the electrical performance and whether the site as built matches the site as documented, so that problems show up while they can still be priced into the deal or fixed by the seller.

    Do grid compliance studies transfer to a new owner?

    The connection agreement and its obligations transfer with the site, and the original studies stay its compliance evidence. Whether they still describe the site is the question to ask, especially if inverters or other equipment have been replaced or modified since commissioning. Lenders and insurers increasingly want that checked rather than assumed.

    Which studies should I redo when buying a solar farm?

    Start with a review of the compliance evidence against the connection agreement. Then check grid code performance (voltage control, frequency response, fault ride through, reactive power), the protection settings, and power quality, which in the UK means a G5/5 harmonic assessment and P28 and P29 studies. Finish with a walk round the site against the as-built drawings.

    Tags

    solar farm technical due diligencesolar farm acquisition due diligencegrid code compliance studies UKG99 complianceG5/5 harmonic assessmentP28 studyP29 study

    Working on a project like this?

    Talk to our engineering team about your site, your grid connection or your power quality problem.

    Get in touch
    GET IN TOUCH

    Let's Solve Your Power Challenge.

    Send an enquiry to our engineering team. We'll help you identify risks and uncover efficiency opportunities.

    North America

    Renewable Energy & Drives

    5325 S Moorland RdNew Berlin, WI 53151United States

    UK & Europe

    Severn Drives & Energy

    Units 2 & 3, Kingsley Business ParkNew Road, Kibworth BeauchampLeicestershire, LE8 0LEUnited Kingdom

    Send an enquiry

    Fill out the form below and we'll be in touch.